SH 3510—2000

中华人民共和国行业标准

Industrial Standard of the People's Republic of China

石油化工设备混凝土基础工程

施工及验收规范

Specification for the construction and acceptance of

petrochemical equipment concrete foundation

Issuance:26-10-2000

Issued by the State Bureau of Petroleum and Chemical Industry

中华人民共和国行业标准

Implementation:01-03-2001

Industrial Standard of the People's Republic of China

石油化工设备混凝土基础工程

施工及验收规范

Specification for the construction and acceptance of

petrochemical equipment concrete foundation

SH 3510-2000

Mainly prepared by: Building and Installation Engineering Co. of Beijing Yanshan

Petrochemical Co., Ltd.

Authorized by: China Petroleum and Chemical Group Co.

— 1 —

Approved by:

State Bureau of Petroleum and Chemical Industry

Beijing 2000

Notice for the Approval of 27 Petrochemical Industrial Standards

Such As“Code for Design of Plantation

in Petrochemical Plant Area”

Sinopec,

This is to notify that we have approved your protocol with regard to 27 petrochemical

industrial standards such as Code for Design of Plantation in Petrochemical Plant Area.

These standards are allowed for release with the following individual number and

designation:

Compulsory standards:

1. SH3008-2000 Code for Design of Plantation in Petrochemical Plant Area(to

replace SHJ 8-89)

2. SH3011-2000 General Rule for Design of Process Equipment Layout in

— 2 —

3. SH3012-2000

4. SH3038-2000

5. SH3504-2000

6. SH3506-2000

7. SH3510-2000

Recommended standards:

8. SH/T3002-2000 Guideline for Design of Energy-Saving Petroleum Warehouse(to

replace SHJ2-87)

9. SH/T3003-2000 Guideline for Design of Reasonable Energy Utilization In

Petrochemical Industry(to replace SHJ3-88)

10.SH/T3013-2000 Code for Design of Vertical Layout for Petrochemical Plant Area

(to replace SHJ13-89)

11.SH/T3101-2000 Legend of Refinery Flowchart(to replace SYJ1002-81)

12.SH/T3102-2000 Design Legend for Heating, Ventilation and Air Conditioning in

Petrochemical Industry(to replace SYJ1005-81)

13.SH/T3104-2000 Code for Design of Instrument Installation in Petrochemical

Industry(to replace SYJ1010-82)

14.SH/T3105-2000 Plot Plant Legend and Code Number for the Automatic Instrument

Piping in Refinery(to replace SYJ1012-82)

15.SH/T3107-2000 Code for Design of Railway Loading Facility of Petrochemical

Liquid Stream(to replace SYJ1020-82)

16.SH/T3108-2000 Code for Design of the Whole Process and Thermal Piping in

Refinery(to replace SYJ1024-83)

17.SH/T3112-2000 Engineering Specification for the Tube Expansion Joint of Tube-

Type Furnace in Petrochemical Industry(to replace SHJ1039-84)

18.SH/T3113-2000 Engineering Specification for the Burner of Tube-Type Furnace

in Petrochemical Industry(to replace SHJ1040-84)

19.SH/T3114-2000 Engineering Specification for Thermal-Resistant Castings of

Tube-Type Furnace in Petrochemical Industry(to replace

SHJ1043-84)

20.SH/T3115-2000 Engineering Specification for Light Grouted Liners of Tube-Type

Furnace in Petrochemical Industry(to replace SHJ1045-84)

21.SH/T3116-2000 Calculation Methods for Consumed Electricity Duty in Refinery(to replace SHJ1067-85)

22.SH/T3117-2000 Calculation Methods for the Consumption of Design

— 3 —

Petrochemical Industry(to replace SHJ11-89)

General Rule for Design of Piping Layout in Petrochemical

Industry(to replace SHJ12-89)

Code for Design of Electrical Installations in Petrochemical

Industry(to replace SHJ38-91)

Code for Construction and Acceptance of Equipment of Regeneration

System in Catalytic Cracker Plant(to replace SHJ504-86)

Code for Construction and Acceptance of Tube-type Furnace

(to replace SHJ506-87)

Code for Construction and Acceptance of Concrete Foundation of

Petrochemical Equipment(to replace SHJ510-88)

23.SH/T3118-2000

24.SH/T3119-2000

25.SH/T3120-2000

26.SH/T3121-2000

27.SH/T3122-2000

The above Standards will be implemented from March 1, 2001, and the replaced Standards

will be abolished at the same time.

Regards,

The State Administration of Petroleum & Chemical Industry

Oct. 26,2000

Thermodynamic Mediums in Refinery(to replace SHJ1069-85)

Code for Design of Steam Jet Evacuator in Petrochemical Industry(to replace SHJ1073-86)

Code for Design of Steel Double Pipe Heat Exchanger in

Petrochemical Industry(to replace SHJ1074-86)

Code for Design of Jet Mixer in Petrochemical Industry(to replace

SHJ1075-86)

Technical Provision for the Process Design of Refinery Plant(to

replace SHJ1076-86)

Technical Provision for the Design of Process Piping Flow in Refinery

(to replace SHJ1077-86)

— 4 —

Contents

1. General Provisions„„„„„„„„„„„„„„„„„„„„„„„„„„5

2. Basic Rules„„„„„„„„„„„„„„„„„„„„„„„„„„„„„6

3. Form panel, steel reinforcement and concrete works„„„„„„„„„„„„8

3.1 Form panel works„„„„„„„„„„„„„„„„„„„„„„„„„8

3.2 Steel reinforcement works„„„„„„„„„„„„„„„„„„„„„9

3.3 Concrete works„„„„„„„„„„„„„„„„„„„„„„„„„11

4. Unbonded prestressed concrete„„„„„„„„„„„„„„„„„„„„15

5. Pre-embedded works„„„„„„„„„„„„„„„„„„„„„„„„18

5.1 Installation of pre-embedded foundation bolt„„„„„„„„„„„„„„18

5.2 Installation of pre-embedded parts„„„„„„„„„„„„„„„„„„20

5.3 Installation of prepared hole form and sleeve„„„„„„„„„„„„„„22

5.4 Drilling and anchoring foundation bolt„„„„„„„„„„„„„„„„25

6. Construction joint of concrete„„„„„„„„„„„„„„„„„„„„„28

7. Grouting„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„30

8. Acceptance of works„„„„„„„„„„„„„„„„„„„„„„„„„32

Appendix A Mixture ratio of epoxy mortar for reference„„„„„„„„„„„„33

Appendix B Mixture ratio of mini-expansive fine gravel concrete for reference „„33

Appendix C Mixture ratio of fine gravel concrete for reference „„„„„„„„„34

Interpretation of the words used in the specification„„„„„„„„„„„„„34

Annex: Interpretation of the Clauses and Articles„„„„„„„„„„„„„„35

— 5 —

1. General Provisions

1.0.1 This specification is applicable for the construction and acceptance of the cast-in-site

concrete structure works for solely bearing equipment in petrochemical industry (hereinafter

referred to as equipment foundation). It is also available for reference for the equipment

foundation of corollary works.

This specification is not applicable for the precast reinforced concrete structure works of

bearing equipment.

1.0.2 All raw materials, semi-finished products and finished products shall conform to the

designed specifications and their quality certificates shall be provided. They shall be

re-examined according to the relevant regulations.

1.0.3 The corrosion-proof works for equipment foundation shall conform to the relevant

regulations on the GB50212 “Specifications for the Construction and Acceptance of Building

Corrosion-proof Works”. The construction and acceptance of pile foundation and bearing

platform shall be executed in accordance with the JGJ94 “Specification for Building Pile

Foundation”.

1.0.4 The safety technology, labour protection and fire precautions shall conform to the

relevant regulations on the SH3505 “ Specification for the Petrochemical Construction

Safety”.

— 6 —

2. Basic Rules

2.0.1 Before the commencement of equipment foundation, the measuring of location and

level marks measuring shall be laid out, taking precautions and making clear signs there.

2.0.2 The construction of equipment foundation shall commence after the base and pile

foundation have been accepted and are qualified. The following items shall be examined

during the acceptance of foundation pit.

1) Coordinate of center and size of foundation pit, elevation and levelness of base surface;

2) Soil of base and treatment of base;

3) Pile distribution, elevation of head of pile, quality of butt of pile, and anchoring

reinforcement bar;

4) Report on acceptance of pile foundation and technical documents of base treatment

2.0.3 The foundation pit shall be excavated in layers, with no more than 1.0m difference in

elevation. The disposal of excavated earth is not allowed to impact the stability of slope of

foundation pit. During excavate earth by machinery, shall protect pile shaft in pit from

damaging.

2.0.4 All the concrete chips from the head of prefabricated pile shall be removed. The loose

head of grouting pile and the concrete containing earth shall be removed.

2.0.5 If the soil on the bottom of bearing platform is frozen, expansive and convex, or the

concrete of grouting pile is frozen during construction in winter, all the frozen soil and

concrete shall be removed. The loose soil and deposited water in the head of pile and bottom

of pit shall be cleared thoroughly during construction in rainy season.

2.0.6 It is not allowed to level the surface of pit by filling loose soil. The same materials as

the bedding course of foundation can be used to level the concave where is lower than the

designed elevation.

2.0.7 The equipment foundation is

not allowed to commence until the

nearby underground works with more

depth are completed and are qualified

after back filling of earthwork.

2.0.8 If the equipment foundation is conducted inside a constructed building or near a

building, the precautions shall be taken to protect the structure of building from settling and

damaging.

2.0.9 If there are some adjacent foundations with different depth, firstly the deep foundation

shall be constructed. If the base of shallow foundation is disturbed, the measures shall be

taken to treat the base.

— 7 —

2.0.10 After the acceptance of foundation pit, the construction of foundation shall start in

time. If abnormal phenomena occur in the foundation pit due to interruption for a long time, it

is required to treat and accept the foundation pit again.

2.0.11 Before the installation of foundation bolt, pre-embedded parts and metal supporting

frame, the grease, oxide and soil on their surface shall be cleared.

2.0.12 The settlement observational point for equipment foundation shall be set in

accordance with the design document and shall conform to the relevant regulations on the

GBJ202 “Specification for the Construction and Acceptance of Base and Foundation Works”.

2.0.13 The settlement observational time shall conform to the following regulations, if it is

not stated in the design.

1) After the complete of grouting concrete and removing the diaphragm plate;

2) Before installation of equipment;

3) After installation of equipment;

4) During test for hydraulic pressure of equipment

5) After drainage of water in testing pressure of equipment, or after trial running of single

machine;

6) The observational times shall be increased in special conditions.

2.0.14 When the foundation is turned to installation of equipment, the strength of concrete

shall conform to the following regulations:

1) For the equipment foundation of block type, it shall be no less than 75% of designed

strength;

2) For the equipment foundation of frame type, it shall be no less than 80% of designed

strength;

3) For the equipment foundation of tower type, it shall be 100% of designed strength;

4) Where the equipment foundation for anchoring foundation bolt, it shall be 100% of

designed strength;

2.0.15 Before the foundation is turned to installation, its axis, elevation and value of

elevation shall be marked.

— 8 —

3.Form panel, steel reinforcement and concrete works

3.1 Formworks

3.1.1 The installation scheme, as well as type, size and quantity of form panel shall be

selected according to the construction drawing. The form panel shall be cleared and repaired

before it is used. During installing the form panel, the joints shall be compactive.

3.1.2 The contacting surface between the form panel and concrete should be coated with

insulating agent before they are used. The partial form panel of foundation reached above of

ground shall be coated with the insulating agent that is no pollution to concrete surface.

3.1.3 During installation of the form panel, the foundation axis and outline shall be prepared

on the concrete mattress or base plate.

3.1.4 During install the column form panel on the frame foundation, the clean out shall be

prepared at the bottom of the column form panel. The operating hole shall be prepared in each

2m of shaft of column form panel. During the construction of steel formwork, a form panel

can be removed as a clean out or an operating hole where it is necessary. Where the section of

structure is small, the steel reinforcement is dense, or the operation is difficult, the through

operating hole shall be set, which the form panel shall be sealed while grouting concrete.

3.1.5 The counter-draw bolt of M12 shall be set on both sides of form panel of wall-type

foundation. The space of counter-draw bolt can be laid by calculation, or according to the

following table 3.1.5.

Table 3.1.5 Space of Counter-draw bolt Layout

Side pressure of concrete(kPa)

≤20

≤40

≤60

3.1.6 If there are trenches for pipeline in the equipment foundation, during the installation of

form panel of foundation, the precast concrete trench can be installed on the shaped steel

supports and can be casted in place with the foundation concrete.

3.1.7 The form panel and supports can be removed according to the following regulations, if

— 9 —

Space of counter-draw bolt (mm)

it is not required in design.

1) When removing the form panel, the strength of foundation concrete shall not be less than

the parameters stipulated in the following table 3.1.7.

Table 3.1.7 Strength of Concrete of Foundation during

Removing the Form Panel

No.

1

Type of structure Span of structure (m)

≤2

Panel (bottom form)

2~8

≤4

Beam (bottom form)

>4

≤2

Cantilever beam (bottom form)

Block foundation

>2

Percentage of designed

strength (%)

50

75

75

100

75

100

40

2

3

4

2) The procedures of removing form panes shall be in reverse to the order of its installation.

In general, firstly the side form panel shall be removed, then the bottom form panel shall

be removed; firstly the column form panel shall be removed, then the beam and platform

form panel shall be removed.

3.2 Steel Reinforcement Works

3.2.1 If any phenomena of brittle rupturing, poor welding or abnormal mechanical

performance occur during the processing of steel bar, the chemical analysis or special

examination shall be adopted.

3.2.2 If the grade and diameter of steel bar that are different from their design, their

replacement shall be approved by the design unit, if necessary.

3.2.3 The joints of steel bar shall be welded. The method of butt-welding will be provided for

the steel bar with more than 22mm of diameter. The welding of steel bar shall conform to the

regulations on the JGJ18 “Rules of Steel Bar Welding and Acceptance ”.

3.2.4 Where the power equipment foundation may be heavily shocked, the method of

welding joints shall not be adopted to connect the steel bar.

3.2.5 Before installation of steel reinforcement, the batching list and plate of reinforcement

shall be checked according to the construction drawings.

3.2.6 As for the frame foundation, if the pre-embedded bolt is contacted with the steel bar at

the connecting place of beam and column, it is necessary to ensure the installation of bolt in

— 10 —

correct position, or ask for the design unit.

3.2.7 As for the laminated place of the hook and hooped reinforcement of beam or column,

the hook and hooped reinforcement shall be staggered along the forced direction of

reinforcement. In the laminated place of the hook and hooped reinforcement of beam, the

hook and hooped reinforcement shall be alternatively placed between the two erected steel

bars. In the laminated place of the hook and hooped reinforcement of column, the hook and

hooped reinforcement shall be alternatively placed at four corners of main reinforcement. The

hooped reinforcement of beam or column shall be perpendicular to the main reinforcement.

The hook and hooped reinforcement shall be made with angle of 135°.

3.2.8 Where there are two meshes of up and down in the foundation reinforcement, the steel

bar and shaped steel can be made into the supports to locate the up mesh of steel

reinforcement.

3.2.9 The thickness of concrete cover for steel bar shall conform to the regulation on the

GB50204 “Specification for the Construction and Acceptance of Concrete Structure Works”.

The tolerance deviation for the concrete cover shall conform to the table 3.2.9.

Table 3.2.9 Tolerance deviation for the thickness of steel

reinforcement cover (mm)

No.

1

2

3

Items

Foundation

Column beam

Panel wall

Tolerance deviation

±10

±5

±3

3.2.10 The galvanized iron wire used for colligating the steel reinforcement shall conform to

the following regulations:

1) No.22 iron wire with diameter of 0.711 mm is suitable for colligating the steel

reinforcement with diameter of 12 mm.

2) No.20 iron wire with diameter of 0.914 mm is suitable for colligating the steel

reinforcement with diameter of 12—25 mm.

3) No.18 iron wire with diameter of 1.219 mm is suitable for colligating the steel

reinforcement with diameter of more than 25mm.

3.2.11 The minimum length of galvanized iron wire used for colligating the steel

reinforcement shall conform to the regulations on the following table 3.2.11

— 11 —

Table 3.2.11 The Minimum Length of Iron Wire used for Colligating

Steel Reinforcement(mm)

Diameter of

steel bar

6

8

10

12

14

16

18

20

22

25

28

32

6

130

8

140

150

10

150

170

180

12

160

170

190

200

14

180

180

200

220

230

16

190

200

220

230

240

250

18

210

220

240

250

250

260

270

20

230

250

250

260

270

280

300

310

22

250

260

260

270

280

300

310

320

340

25

270

280

280

290

300

310

330

340

350

370

28

300

300

310

310

320

330

350

360

370

390

400

32

320

330

340

340

350

360

370

380

390

410

430

450

3.3 Concrete Works

3.3.1 Before grouting the concrete on foundation, the following items shall be checked and

conform to their specifications:

1) Axis, elevation and location;

2) Form panel and steel reinforcement;

3) Pre-embedded foundation bolt, prepared hole form, pre-embedded parts and metal

supports.

3.3.2 The test report of mixture ratio for foundation concrete shall be provided.

3.3.3 The same type and same mark of cement produced by the same factory shall be

provided for the same foundation concrete.

3.3.4 It is forbidden to add the additive containing chloride to the reinforcement concrete.

3.3.5 The operating platform shall be provided during grouting the concrete. It is forbidden to

stand on the reinforcement for operation.

3.3.6 Before construction of concrete, the material reserve, mixing and conveying capacity

shall be planed and the grouting scheme of concrete shall be prepared. If possible, the

premixing concrete shall be provided.

3.3.7 During the construction of bulk concrete, the temperature differential between inside

— 12 —

and outside the foundation shall not exceed 25℃. To protect the concrete from cracking, the

following measures can be selected to reduce temperature.

1) Use the cement with low heat of hydration;

2) Add the additives with functions of slowly setting or mini-expanding;

3) Increase the content of coal ash to decrease the cement;

4) The water cement ratio is no more than 0.55;

5) Add the rubble stone with size 200mm, which accounting for 15%--25% of the total

quantity.

6) Strengthen the thermal curing to slowly radiate on the surface of foundation. After the

concrete finally setting, the curing by ponding shall be provided.

7) Embed the circulating water pipe in foundation to radiate.

8) Be mixed with ice.

9) Take measures to reduce the temperature of soil and gravel.

3.3.8 The concrete near the foundation bolt, pre-embedded parts, prepared hole form and

pre-embedded pipeline shall be compacted by vibrating to avoid impact. It is necessary to

check the displacement deviation during construction.

3.3.9 In constant temperature, the concrete shall be covered and cured by watering after 12

hours of grouting. The watering times depend on the wet condition of concrete. No less than 7

days of curing period is required. If the concrete is added by the slowly setting addition agent,

no less than 14 days of curing period is required.

3.3.10 The margin of concrete trial block with the same mixture ratio shall conform to the

following requirements:

1) No less than two groups per working shift;

2) No less than one group per 50m3.

3.3.11 The work qualities of equipment foundation shall conform to the following

requirements:

1) No any defects of crack, honeycomb and exposed bar occur;

2) The earthwork around the foundation shall be back filled, tamped and trimmed in time.

3) No any damage and erosive bolt and pre-embedded-parts occur.

4) Shall clean the water and foreign matter inside the prepared bolt hole.

5) The tolerance deviation of equipment foundation shall conform to the regulations on the

table 3.3.11-1 and the table 3.3.11-2.

6) As for the equipment foundation consisting of many blocks of sole foundation, the

tolerance deviation of axis and elevation for each foundation shall be checked according

— 13 —

to the table 3.3.11-1.

Table 3.3.11-1. The Tolerance Deviation for Block Equipment Foundation (mm)

No.

1

Items

Axis

position

Elevation at different level (exclusive of the thickness of grouting surface)

Overall dimension of plane

Overall dimension of plane on convex

0

-20

±20

0

-20

+20

0

5

10

5

10

+10

0

±2

10

+20

0

10

+10

0

5

5

0

+5

10

5

Tolerance Deviation

20

2

3

Dimension of plane on concave

Levelness (inclusive of the plane to

Per meter

be installed equipment)

Overall length

Per meter

Overall height

Elevation (top)

Pre-embedded foundation bolt

Central space (check both at the

bottom and top)

Central line

7 Prepared hole for foundation bolt Depth

Plumbing for central line of hole

Elevation

8

Pre-embedded mobile anchor slab

of foundation bolt Central line position

levelness

Elevation (plane)

9 Pre-embedded parts

Central line position

levelness

4

5 Side verticality

— 14 —

— 15 —

Table 3.3.11-2. The Tolerance Deviation for Frame Equipment Foundation (mm)

No.

1 Axis position

Items

foundation

Column and gird

Per layer

Overall height

Per layer

3 elevation

Overall height

4

5

Section size

Levelness (use 2m ruler to check)

Pre-embedded parts

6

Central line of pre-embedded

facility Pre-embedded foundation bolt

Pre-embedded pipe

7 Central line for prepared hole

2

5

10

Tolerance deviation

15

8

5

H/1000 is no more than 20

0

-10

0

-20

+8

-5

8

2 Verticality

Note: H—the overall height of structure

3.3.12 The defect of the performance of concrete structure shall be treated together with the

designed unit. The repair for the defect of foundation surface shall conform to the regulation

on the GB50204 “ Specification for the Construction and Acceptance of Concrete Structure

Works”.

— 16 —

4. Unbonded prestressed concrete

4.0.1 The stranded steel wire and the steel wire used for the unbonded prestressed concrete

shall conform to the regulations on the GB5224 “Stranded Steel Wire for Prestressed

Concrete” and the GB5223 “Steel Wire for Prestressed Concrete”.

4.0.2 The construction and acceptance of unbonded prestressed concrete shall conform to the

regulations on the GB50204 “Specification for the Construction and Acceptance of Concrete

Structure Works”.

4.0.3 The side form panel on the foundation plate of unbonded prestressed concrete shall

conform to the following regulations:

1) The fixed bearing form panel shall be wood form or wood-and-steel form panel.

2) The snapping the line, marking and drilling for the form panel shall be conducted with

the diameter of unbonded strong stranded steel wire (hereinafter referred to as unbonded

reinforcement) and its location.

3) The tolerance deviation for the verticality of form panel for fixing pre-embedded bearing

plate shall be no more than 3 mm.

4.0.4 The layout of unbonded reinforcement shall conform to the following regulations:

1) The factors as laying order, location of supports and prepared hole for steel

reinforcement shall be comprehensively considered with the layout of common steel

reinforcement during the layout of unbonded steel reinforcement.

2) No joints and bend in the unbonded reinforcement are required.

3) No less than 500 mm of exposed unbonded reinforcement length out of the form panel at

the tension end. If the unbonded reinforcement is short of length, firstly shall ensure the

exposed length at the tension end.

4) The maximum gap between the anchor end and the edge of foundation shall be controlled

within 200 mm.

5) The vertical length of axis of unbonded reinforcement and the bearing plate shall be no

less than 500 mm.

6) As for the hole and port, the unbonded reinforcement shall be constructed according to

the figure 4.0.4 and shall be added with shape-V tension reinforcement at the bend

position.

— 17 —

Figure 4.0.4 Unbonded Reinforcement At Port

7)

The gap of 100 mm between the unbonded reinforcement and the edge of structure shall

be set.

8) Each pier of unbonded reinforcement shall be closely contacted with the anchor slab,

where there is any gap, the anchor slab shall be hammered to closely contact with the pier

of steel wire.

9) The gap between the installation of screw reinforcement and the anchor slab or the

bearing plate shall be 50 mm. Use the iron wire to colligate the screw reinforcement on

the unbonded reinforcement.

10)The unbonded reinforcement shall be colligated with iron wire and laid in level. The

tolerance deviation in vertical shall be 5 mm. The tolerance deviation in horizon shall be

30 mm.

4.0.5 The construction of unbonded reinforcement shall conform to the following

requirements.

1) The buffer plate shall be provided at the feeding place so as to protect the unbonded

reinforcement from flushing of great amount of concrete.

2) It is forbidden that the vibrator impacts the unbonded reinforcement, screw

reinforcement, anchor slab and bearing plate during vibrating.

3) The concrete shall be grouted at one time, without construction joints.

4.0.6 The concrete strength shall be no less than 75% of the design standards during tension

of unbonded reinforcement.

4.0.7 The tension of unbonded reinforcement shall conform to the following requirements.

1) The stress shall be mainly controlled and checked with strain for pretensioning.

2) The method of supertension shall be adopted to reduce the impact of unbonded

reinforcement, from the zero stress tension to the 1.03 times of controlled stress. The

maximum tension stress shall not exceed the 75% of the tensile stress stated.

3) Before construction, the appliance and instrument such as oil pump, hydraulic jack and

tool anchor shall be checked, and the gauge pressure for the oil pump shall be set.

— 18 —

4) Before the wedge anchorage is used, the static test for its assembly shall be conducted

according to the relevant regulations. The efficiency of anchorage and the anchoring

capacity shall be tested and the anchorage shall be greased to avoid rust and erosion.

5) Before tension, the mortar at the end of bearing plate shall be cleared and the plastic

sleeve of exposed unbonded reinforcement shall be removed.

6) Before tension, record the exposed length of unbonded reinforcement in their numbers.

Record the second measures after tension. The differential of both records is the actual

extension value. The actual extension value shall be no more than 10% of its designed

value, or no less than 5% of its designed value.

7) If any steel wire releases or cracks during tension of unbonded reinforcement, the tension

shall be relieved. The released or cracked wires shall be no more than 2% of the total in

the same section of unbonded reinforcement.

8) During pretensioning, the workers shall stand on both sides of jack to avoid the damage

from jack.

9) The method of symmetrical tension shall be adopted.

4.0.8 The strict precautions for sealing in the unbonded anchor zone shall be provided. The

construction of sealing concrete shall conform to the following requirements:

1) A length of 200mm unbonded reinforcement shall be prepared outside the foundation.

Remove the exposed unbonded reinforcement with non-tooth saw. If use the

oxy-acetylene flame to cut it, a length of 250mm shall be prepared.

2) Disperse and bend the prepared unbonded reinforcement.

3) Clean the chips of concrete at both sides of structure and grout the same grade of concrete

as the structure.

4) The sealed concrete at ends shall be solid inside and smooth outside.

5) Coat the heating bituminous or other corrosion-proof paint on the surface of sealed end of

concrete.

— 19 —

5. Pre-embedded works

5.1 Installation of pre-embedded fundation bolt

5.1.1 The foundatin bolt, nut and anchor slab of bolt shall be made up of non-cold-drawing

steel of type Q235-A.F if no specification for their materials is stipulated in design.

5.1.2 The foundation bolt and nut shall be matched, with proper tightness and without any

defect and crack on screw thread. If no specification is stipulated in design, the structure of

foundation bolt shall conform to the following regulations (figure 5.1.2)

Figure 5.1.2

1) The pre-embedded depth of square hook bolt or U-bolt shall be no less than 20 times of

the bolt diameter. The length of square hook shall be no less than 4 times of the bolt

diameter. The centre distance of U-bolt is the same as the centre distance of bolt hole for

installing equipment base.

2) The total cramp section shall be no less than 2/3 of the bolt section, which shall be evenly

welded at the down end of bolt.

3) The anchor slab thickness of slab-type bolt shall be no less than 8mm. The plan

dimension shall be no less than 80 × 80 (mm). The pre-embedded depth of

anchor-slab-type foundatin bolt shall be no less than 15 times of bolt diameter.

5.1.3 The pre-embedded foundation bolt on equipment foundation shall be fixed by the

locating form panel. The locating form panel shall be made up of steel, with proper strength

and rigidity.

5.1.4 After the locating form panel is fixed with bolt, no any oscillation occurs.

5.1.5 The selection of structure of locating form panel shall depend on the exposed length,

diameter, quantity and distribution of bolt (figure 5.1.5-1, figure 5.1.5-2). The double-layer

locating form panel is suitable for the tower-type equipment foundation and the single-layer

— 20 —

locating form panel is suitable for the common equipment foundation.

Figure 5.1.5-1 Sketch of locating form panel in round foundation

Figure 5.1.5-2 Sketch of locating form panel in square foundation

5.1.6 The mechanical processing method shall be adopted in the bolt hole on the locating

form panel. The bore diameter shall be 1mm more than its bolt diameter. The tolerance

deviation of locating form panel shall conform to the regulations on table 5.1.6.

Table 5.1.6. The tolerance deviation of locating form panel (mm)

ItNo. ems

1

2

3

Overall dimension

Levelness of surface

B±5

2

+0.5

Tolerance deviation

— 21 —

ore

diameter

4

5

6

Pitch of holes

Coaxality of up and down bores

Diagonal line of bolt hole, or diameter of central circle

0

±1

1

±1

5.1.7 The small locating form panel can be directly borne on the form panel of foundation

during installation. The large locating form panel shall be supported with shape steel supports

during installation and shall conform to the following regulations.

1) Embed the pre-embedded parts of fixed supports on the concrete mattress or concrete bay

of foundation.

2) Lay out the axis of foundation on the mattress or bay.

3) Install the supports, locating form panel and bolt and fix them temporarily.

4) Colligate the steel bar and install the form panel and pre-embedded parts.

5) Check the axis, levelness and elevation of locating form panel, fix it on the support by

welding and weld sufficient braces and rods on it.

6) Fix both surfaces of up and down of locating form panel with bolt (nut).

5.1.8 The installation of locating form panel shall conform to the following regulations.

1) The column for support shall be arranged regularly and symmetrically.

2) The bottom of locating form panel shall be at least 50 mm higher than the top of

foundation.

5.1.9 Dont damage the thread of bolt during remove the locating form panel.

5.1.10 Before grouting concrete, the exposed thread of foundation bolt shall be coated with

the lubricating grease and shall be wrapt with plastic film.

5.2 Installation of Pre-embedded Parts

5.2.1 Before construction of foundation, the necessary pre-embedded parts shall be checked.

If there are a lot of pre-embedded parts and different types, the installation drawing of

— 22 —

pre-embedded parts shall be made out.

5.2.2 Before installation, the type, size, quantity and welding quality of steel plate and anchor

steel reinforcement shall be checked. Leveling shall be provided for the large pre-embedded

parts and exhaust hole shall be set according to its requirement.

5.2.3 If use the steel form panel, the following methods can be selected for fixing the side

pre-embedded parts.

1) Bolt fixation (figure 5.2.3-1):

— 23 —

Figure 5.2.3-1 Bolt fixation

2) Welding Fixation (figure 5.2.3-2):

Figure 5.2.3-2 Welding fixation

3) Inserted Wood Plate Fixation (figure 5.2.3-3):

— 24 —

Figure 5.2.3-3 Inserted Wood Plate Fixation

5.2.4 The following methods can be selected for the installation of top of foundation.

1) Firstly mark it, compact and level the surface of concrete, and then install it.

2) As for the large pre-embedded parts, firstly install it and then grout the concrete. Erect

the bearing support for fixation when installation.

5.2.5 After the form panels for foundation, the grout and concrete on the pre-embedded piece

shall be removed in time, and elevation and center line shall be remarked.

5.3 Installation of Prepared Hole Form and Sleeve

5.3.1 The prepared hole form for bolt shall be made up of wood or steel, with no less than 3%

grade for pulling form.

5.3.2 As for the depth of prepared hole exceeds 1 meter, the hole form shall be made up of

steel tube, with sealed cone at bottom of tube. The hole form shall be fixed at both ends of up

and down and shall be cared by person. Don’t damage the surface of foundation during

pulling the form after initial setting.

5.3.3 Dont coat the machine oil on the form of hole as insulating agent.

5.3.4 The gap between the edge of the prepared hole for bolt and the edge of foundation shall

be no less than 100mm. The gap between the bottom of the prepared hole for bolt and the

bottom of foundation shall be no less than 100mm.

5.3.5 Clean the water, soil and foreign matter inside the prepared hole and then seal the hole.

5.3.6 As for the pre-embedded sleeve for gird and side of wall, the steel bar shall be welded

into the headframe to cramp the sleeve. The headframe steel bar shall be welded with the

main steel reinforcement (figure 5.3.6).

— 25 —

Figure 5.3.6 Fixing sleeve with steel headframe

5.3.7 The following methods can be selected for installation of form of hole and sleeve on the

steel form panel of concrete platform.

1) As for the installation of round form of hole, firstly fix a round wood table on the steel

form panel with wood screw and then put the form of hole on it (figure 5.3.7-1).

Figure 5.3.7-1 Fixing form of hole on a round wood table

2) As for the installation of small square form of hole, fix a locating wood block on the steel

form panel and insert the wood wedge after put the form of hole on it (figure 5.3.7-2).

— 26 —

Figure 5.3.7-2 Fixing form of hole with locating wood block

3) As for the installation of large form of hole, a space for laying the steel form panel shall

be prepared and the diagonal brace shall be used to fix the form of hole on the steel form

panel (figure 5.3.7-3).

Figure 5.3.7-3 Fixing form of hole by bracing

4) If the hole is close to the side form panel, fix the form of hole on the side form panel by

tie method (figure 5.3.7-4).

— 27 —

Figure 5.3.7-4 Fixing form by tie method

5.3.8 The tolerance deviation for installation of pre-embedded foundation bolt, pre-embedded

parts, pre-embedded sleeve and prepared hole shall conform to the regulations on table 5.3.8.

Table 5.3.8 The tolerance deviation for installation of pre-embedded foundation bolt,

pre-embedded parts, pre-embedded sleeve and prepared hole (mm)

Items Tolerance Deviation

Central position

1

Elevation at top

1

+5

0

— 28 —

Verticality

3‟

2

3

Central position of pre-embedded parts

Central position of pre-embedded sleeve

Central position of prepared hole of bolt

5

3

5

+20

0

5

4 Depth

verticality

Central position

Prepared

hole

Inside dimension of section

5

+10

0

5

5.4 Drilling and Anchoring Foundation Bolt

5.4.1 If drill hole on the foundation and use the epoxy resin mortar, mini-expansive fine

gravel concrete and high strength non-shrinking grout to anchor the foundation bolt, shall

conform to the following requirements:

1) In order to increase the anchoring strength, turn the thread on the pre-embedded section

of bolt and clean the oil and grease.

2) The rough wall inside the hole of pre-embedded bolt is required. Blow out the dust inside

the hole.

— 29 —

3) Select the bonding materials with qualified specifications and its compressive strength

shall be no less than 30MPa.

4) Make trial of its mixture ratio before construction. Make trial of its pulling resistance for

the anchored foundation bolt at the same conditions.

5) The mixing time for bonding materials shall be no less than 2 minutes. Grout the concrete

in succession while mixing.

6) It is required to make trial block according to its design.

7) When the hole of foundation bolt is formed, the strength of foundation concrete shall be

no less than 20MPa.

8) The temperature of construction environment shall be at least 5℃ and curing for it is

required after construction.

9) The anchored depth for bolt shall be no less than 15 times of the diameter of bolt if no

specification in design.

10)The tolerance deviation of central position for hole of bolt shall be no more than 2mm.

The tolerance deviation of verticality for hole of bolt shall be no more than 1% of the

depth of hole.

5.4.2 When use the epoxy mortar to anchor the foundation bolt, its specifications shall also

conform to the following regulations:

1) If the diameter of bolt is 12—22mm, the gap between the surface of bolt and the wall of

hole shall be no less than 8mm. If the diameter of bolt is 24—42mm, the gap between the

surface of bolt and the wall of hole shall be no less than 15mm.

2) Keep dry on the wall of hole.

3) The medium sand and coarse sand can be used after they are washed and dried. It also

uses the quartz sand.

4) The mixture ratio of epoxy mortar is shown in the Appendix A.

5.4.3 When use the mini-expansive fine gravel concrete to anchor the foundation bolt, its

specifications shall conform to the following regulations:

1) If the diameter of bolt is 12—22mm, the gap between the surface of bolt and the wall of

hole shall be no less than 20mm. If the diameter of bolt is 24—42mm, the gap between

the surface of bolt and the wall of hole shall be no less than 30mm.

2) Keep wet on the wall of hole, but no water inside.

3) The diameter of gravel shall be 5—10mm and the water shall be potable water.

4) The curing period shall be 3—7 days. When the strength of trial block reaches 30MPa, it

can be turned to next procedure.

5) The mixture ratio of mini-expansive fine gravel concrete is shown in Appendix B for

— 30 —

reference.

5.4.4 When use the high strength non-shrinking grout to anchor the foundation bolt, its

specifications shall also conform to the following regulations:

1) The drilling diameter shall depend on the diameter of foundation bolt. The gap between

the surface of bolt and the wall of hole shall conform to the regulations on the table 5.4.4.

Table 5.4.4. The gap between the surface of bolt and the wall of hole (mm)

Diameter of bolt

12~24

16~22

24~42

Gap between the surface of bolt and the wall of hole

≥8

≥15

≥20

1) Dont add any addition agent to the high strength non-shrinking grout.

2) Dont vibrating and inserting tamp concrete during anchor grouting. Don’t adjust the bolt

after grouting.

3) If bleeding occurs on the surface during grouting, the drying agent shall be spread to

absorb the moisture.

— 31 —

6. Construction Joint of Concrete

6.0.1 Dont set the construction joint for the equipment foundation to bear power force. If it is

necessary to set the construction joint, shall ask for the design department.

6.0.2 The construction joint shall be set according to follows:

1) The construction joint shall be set into a horizontal joint or vertical joint, but not a

diagonal joint.

2) The horizontal joint usually shall be set on the upper surface of foundation base, or shall

be set on the place where the structure is easy to be constructed and is borne by less

shearing stress.

3) The vertical joint for pile bearing platform shall be set on the 1/3 space between two

piles.

4) Dont set the construction joint on the cantilever of foundation and weak place of hole.

6.0.3 Setting the construction joint in the zone of foundation bolt on equipment foundation

shall conform to the following regulations:

1) The horizontal joint shall be lower than the bottom of foundation bolt and its distance

shall be more than 150mm. As for the foundation bolt with diameter of less than 30mm,

the horizontal joint shall be set on the place where is at least3/4 of the total length of

foundation bolt pre-embedded in concrete.

2) The distance between the vertical construction joint and the central line of foundation

bolt shall be no less than 250mm. The vertical construction joint shall be no less than 5

times of the diameter of bolt.

6.0.4 The treatment of construction joint of concrete on equipment foundation shall conform

to the following regulations:

1) As for the two horizontal construction joints at different elevation, the joint between high

and low places shall be set to a bench. The ratio of height to width of the bench shall be

no more than 1.

2) It shall add the horizontal inserted steel reinforcement in the vertical construction joint.

Its diameter shall be 12~16mm and its length shall be 500~600mm. Insert the half of its

length, with gap of 500mm.

3) It is not allowed to next grout concrete until the compressive strength of concrete at the

construction joint reaches 1.2Mpa. The time of the compressive strength of concrete

reaches 1.2Mpa is shown in the table 6.0.4 for reference.

— 32 —

Table 6.0.4 The shortest time of the compressive strength of

concrete reaches 1.2MPa (h)

Temperature of environment

Type of cement

1~5 ℃

Portland cement

Portland-slag cement, Pozzolan cement

60

90

5~10℃

48

72

10~15℃

36

48

over15℃

24

36

1) Check the foundation bolt before the next grouting.

2) Remove the chips on the surface of concrete of construction joint and clear the soft and

weak concrete. Before the next grouting, shall wash the surface with water. After the

concrete is wet, shall put a thickness of 30—50 mm of cement mortar with the same

contents as the concrete.

3) Shall carefully tamp the concrete at construction joint to ensure the compactness of old

and new concrete.

6.0.5 Shall take down the records of location of construction joint and its treatment method.

— 33 —

7. Grouting

7.0.1 It is required to go through the formalities of middle handing over before grouting the

equipment foundation. Unless otherwise specified in design drawings, the margin for the

second grouting on the top of foundation shall be provided. A margin of 30mm for the

grouting on top of common foundation and a margin of 50mm for the grouting on top of large

equipment foundation and tower-type equipment foundation shall be provided.

7.0.2 Before grouting on foundation, the foundation shall be treated as follows:

1) The surface of foundation for grouting shall be chiselled to pitting, with 3—5 pits in an

area of 100 × 100 (mm). It also can be rough treated when the initial setting of

foundation concrete.

2) Shall chisel off the grease concrete.

3) Wash the surface of foundation with water and keep it wet at least 24 hours. Before 1

hour to grout, the water shall be absorbed.

4) Clear the foreign matter and water inside the prepared hole.

7.0.3 The grouting for the prepared hole of foundation bolt shall start after the initial leveling

of equipment. As for the prepared hole of foundation bolt, it is required to fully grout to the

surface of foundation at one time and tamp it compactly. Protect the equipment from

displacing during tamping.

7.0.4 The second grouting for the base of equipment shall be conducted at one time within

the 24 hours after final leveling of equipment. It is not allowed to grout in layers.

7.0.5 The strength grade of concrete used for grouting fine gravel shall be one grade higher

than that used for foundation. The strength of cement mortar shall be no less than 10MPa. A

high-early strength agent without content of chlorate can be added to the concrete for

high-early strength. The mixture ration of fine gravel concrete is shown as Appendix C for

reference.

7.0.6 When use the mini-expansive concrete for grouting, shall check the raw materials

before construction and shall make a trial of mixture ratio. When use the high strength

non-shrinking materials for grouting, shall check the materials for grouting.

7.0.7 As for the hole of foundation bolt with anchor slab, it shall be constructed according to

the figure 7.0.7, if no specification in design.

— 34 —

Figure 7.0.7 Sketch of grouting hole of foundation bolt with anchor slab

1—foundation bolt;2—nut, washer;3—base;4—iron shims;

5—mortar layer(or fine gravel cement);6—prepared hole;7—foundation;

8—dry sand layer;9—anchor slab;10—second grouting layer

7.0.8 Before the second grouting, it is required to install the outer form panel. The depth of

base of equipment shall be pre-embedded in the second grouting layer with no less than

10mm.

7.0.9 The grouting materials shall be made into trial block and the grouting shall be

conducted while mixing in place. The surface of foundation shall be smooth and shall be

cured by watering in time.

7.0.10 If the environment temperature is at 5℃ below, shall provide the precautions to avoid

freezing of grout during curing.

— 35 —

8. Acceptance of Works

8.0.1 When accept the equipment foundation, the construction unit shall provide the

following handing over technical documents and shall execute the regulations on the SH3503

“Rules on the handing over technical documents of works construction”.

1) List of changing design and list of replaced materials;

2) Certificate of raw materials quality and report of reexamination

3) Test report on the welding joint of steel reinforcement

4) Test report on the concrete mixture ratio and concrete trial block

5) Record on the measurement and location

6) Record of acceptance of concealed works

7) Test report on grouting trial block

8) Certificate of unbonded steel anchorage and cramp and record of examination

9) Record of tension of unbonded steel reinforcement

10)Record of settlement observation of equipment foundation

11)Re-check record of equipment foundation

12)Record of examination of concrete quality

13)Completed drawings and other documents

8.0.2 As for the acceptance of equipment foundation, shall examine its appearance after

execute the above clause 8.0.1 and shall go through the formalities of handing over and

acceptance.

— 36 —

Appendix A Mixture ratio of epoxy mortar for reference

Table A. Mixture ratio of epoxy mortar for reference

No.

1

2

3

4

Name of materials

Epoxy resin

Dibutyl phthalate

ethylenediamine

sand

6101

Used for industry

Used for industry

Medium and coarse sand

Type

Mixture ratio

(% of weight)

100

17

10

250

Appendix B Mixture ratio of mini-expansive fine gravel concrete

for reference

Table B Mixture ratio of mini-expansive fine gravel concrete for reference

Mixture ration of weight Performance of trial block

No.

Ratio of water

cement

Sand Gravel others

Variation ratio

of size

Strength

(MPa)

1 (mark 525

1 0.39 placing

cement )

2 (mark 325

2 0.40 alumina

cement )

0.71 2.03

Gypsum

0.02

Alum 0.02

1.36 2.75 —

0.452/10000

(expanding)

2.4/10000

(expanding)

40

30~50

— 37 —

Appendix C. Mixture ratio of fine gravel

concrete for reference

Table C. Mixture ratio of fine gravel concrete for reference

Grade of

No. concrete

strength

1 C25

Mark of

cement

Cement

349

425

351

394

400

Mixture ratio (Kg/m3)

Sand

631

663

561

650

Stone

1280 (gravel)

1255 (pebble stone)

1260 (pebble stone)

1200 (gravel)

Water

185

200

185

200

2 C30 425

Note: (1) The particle diameter of stone is 5—15mm, the particle diameter of sand is

0.4~0.5mm.

(2) Start to cure by watering after 12 hours of grouting.

(3) The curing period shall be no less than 7 days.

Interpretation of the

words used in the

specification

The words that mean different extent to implement the specification is interpreted as follows:

1) The words of “must” and “forbid” mean that something shall be done at a quite strict

extent.

2) The words of “shall” or “not shall” and “don’t” mean that something shall be done at a

strict extent.

3) The words of “suitable” and “not suitable” mean that something shall be done if possible.

4) The words of “may” means that something can be selected to do on certain conditions.

— 38 —

中华人民共和国行业标准

Industrial Standard of the People's Republic of China

石油化工设备混凝土基础工程

施工及验收规范

Specification for the construction and acceptance of

petrochemical equipment concrete foundation

SH 3510-2000

Interpretation of the Clauses and Articles

Beijing 2000

— 39 —

Contents

1. General Provisions„„„„„„„„„„„„„„„„„„„„„„„„„„35

2. Basic Rules„„„„„„„„„„„„„„„„„„„„„„„„„„„„„35

3. Form panel, steel reinforcement and concrete works„„„„„„„„„„„35

3.1 Form panel works„„„„„„„„„„„„„„„„„„„„„„„„35

3.2 Steel reinforcement works„„„„„„„„„„„„„„„„„„„„„36

3.3 Concrete works„„„„„„„„„„„„„„„„„„„„„„„„„36

4. Unbonded prestressed concrete„„„„„„„„„„„„„„„„„„„„37

5. Pre-embedded works„„„„„„„„„„„„„„„„„„„„„„„„„37

5.1 Installation of pre-embedded foundation bolt„„„„„„„„„„„„„37

5.3 Installation of prepared hole form and sleeve„„„„„„„„„„„„„37

5.4 Drilling and anchoring foundation bolt„„„„„„„„„„„„„„„„37

6. Construction joint of concrete„„„„„„„„„„„„„„„„„„„„„38

7. Grouting„„„„„„„„„„„„„„„„„„„„„„„„„„„„„„38

8. Acceptance of works„„„„„„„„„„„„„„„„„„„„„„„„„38

— 40 —

1. General Provisions

1.0.2 This specification is applicable for the same scope as the original specification with the

exception of some modification in words.

The concrete foundation in the specification includes the foundation of plain concrete,

foundation of steel reinforcement concrete and foundation of non-bonded prestressed

concrete, which is the same as those in the GB50204 “Specification for the construction and

acceptance of concrete structure works”.

1.0.3 The specification for the construction and acceptance of concrete structure works

involves many aspects of raw materials, semi-finished products and finished products.

Therefore, it is required to execute the articles stipulated in the specification. If some articles

are not stipulated in the specification, it is required to execute the relevant specifications and

standards.

1.0.4 Cancel the two articles of “corrosion-proof works” and “pile bearing platform” in the

original specification. The corrosion-proof works of equipment foundation shall be

conducted according to the “specification for the construction and acceptance of building

corrosion-proof works”(GB50212—91). The pile bearing platform works of equipment

foundation shall be conducted according to the “Specification for building pile

foundation”(JGJ—94).

2. Basic Rules

2.0.2 This clause only involves the acceptance of base or pile foundation works. The

specification for construction and acceptance of base and foundation works and the

specification for building pile foundation are stipulated in the national standards. The

interpretation is shown in the construction drawings if necessary.

2.0.3~2.0.5 These clauses are stipulated in the “pile bearing platform”. The article of “pile

bearing platform” has been cancelled in the revised edition. Some of clauses are shown here.

3. Form Panel, Steel Reinforcement and Concrete Works

3.1 Form Panel Works

3.1.4 In this clause, the original clause of “a tamping hole shall be set in each 3m on the form

panel” has been changed to the clause of “an operating hole shall be set in each 2m”. That

means that the hole will be used not only for tamping, but also for other operating such as

grouting. So, this clause will correspond to the clause of “The free height of concrete falling

from high place shall not exceed 2m” on the “specification for construction and acceptance of

— 41 —

concrete structure works”.

3.2 Steel Reinforcement Works

3.2.3~3.2.4 As the power equipment foundation, especially the position where impact stress

is strong and the steel reinforcement is easy to break, some new regulations have been

stipulated here. It is required to adopt the hot rolling steel bar and shall not adopt the welding

to ensure the life of equipment foundation. The original clause that “The steel bar with

diameter of more than 22mm shall be welded by the method of flashing butt welding” has

been changed to the new clause of “by butt welding”. Now, there are many methods in butt

jointing steel bar and the flashing butt-welding is only one of them. After change, the

construction units can select their own welding method according to conditions. Meanwhile,

the requirement for the welder has been cancelled because it has been stipulated in the

“specification for welding and acceptance of steel bar”(JGJ18—84) in detail.

3.2.9 It has cancelled the table 3.2.12 “quality standards of steel reinforcement works” on the

original clause 3.2.12 and only remained the page of “cover of main steel reinforcement”.

Because the article of “specification for construction and acceptance of concrete structure

works” only involves the thickness of the cover of steel reinforcement, which does not

involve the tolerance deviation of thickness. Actually, there is a tolerance deviation in the

cover during colligating steel reinforcement.

3.2.10~3.2.11 These are newly added contents provided for those construction units that

always adopt the same size and same length of iron wire to colligate different steel bars,

which may affect the installation quality of steel reinforcement.

3.3 Concrete Works

3.3.6 At present the measuring in some temporary and simple mixture stations are not

accurate, which strictly affect the quality of concrete, waste materials and pollute the

environment. The extension of premixing concrete has been early required in the “Guidance

of extension of 10 items of new technology in construction industry” in the No.40 [1996]

Ministry of Construction Industry.

3.3.7 During construction for bulk concrete, supplement the clause of “the temperature

differential between inside and outside the foundation shall not exceed 25℃. That will

correspond to the clause of “specification for construction and acceptance of concrete

structure works”. In addition, it also supplement the clause of both measures of reducing

temperature of ice mixing and sand and stone so as to provide feasible scheme for

construction unit selection.

3.3.12 Actually, the exposed bolt on foundation is too long after installation of equipment

and is far away from the requirement of exposed 2—3 threads of nut after installation of

equipment. Here modify some tolerance deviation to be more suitable for the demand in

construction after study and investigation.

3.3.13 It supplements the clause of “Repair for defect concrete”. That will correspond to the

— 42 —

contents of “specification for construction and acceptance of concrete structure works” and

make the specification more complete.

4. Unbonded Prestressed Concrete

This is a newly supplemental content. With the development of high-tech, the technology of

unbonded prestressed concrete has been widely used for combined base of equipment

foundation for its advanced, simple, economic, safe and no-pollutant features. In 1989, the

unbonded prestressed concrete foundation replaced the pile foundation in the construction of

relief equipment foundation in Tianjin Dagang Oil Refinery. The foundation investment was

saved by 30% of the total and the construction period was shorted by half a year. It has been

put into operation for 10 years and has run very well.

5. Pre-embedded Works

5.1 Installation of Pre-embedded Foundation bolt

5.1.1 This is a supplemental clause. As the bolt and nut and anchor-slab of bolt used for the

domestic equipment may be produced by the construction unit, it is necessary to specify the

steel.

5.1.2 This is a supplemental clause. As the bolt and anchor-slab used for the domestic

equipment are usually produced by the owner or the construction unit, which are lack of

specified size, here specify this clause to ensure the processing quality.

This clause is prepared with reference to the “Specification for foundation design of the small

container equipment in oil refinery”.

5.3 Installation of Prepared Hole Form and Sleeve

5.3.4 This is a supplemental clause. Here specify the gap between the edge of prepared hole

and the edge of foundation based on the size of bolt to restrict the construction unit to extend

the hole for easy construction.

5.3.8 In the table 5.3.8, the tolerance deviation of top elevation in installation of

pre-embedded foundation bolt has been changed from the original +10 and 0 to now +5 and 0

so as to short the exposed length of bolt. The verticality has been changed from the 5‟ to 3‟. That will correspond to the tolerance deviation of locating form panel in the clause 5.1.6.

5.4 Drilling and Anchoring the Foundation bolt

This is a supplemental content. It is necessary to drill and embed the foundation bolt when

improve the works and install new equipment on the original equipment foundation. At

present, although there are many methods for drilling and anchoring the foundation bolt,

— 43 —

these methods are in the test period and no specified standards of construction and acceptance

are issued. Here provide some methods for specification.

6. Construction Joint of Concrete

6.0.3 In the area of foundation bolt on equipment foundation, the preparation for construction

joint is a supplemental clause and is made out according to the clause 4.4.21 “specification

for construction and acceptance of concrete structure works ” (GB50204-92).

6.0.4 It supplements the clause 4 of “An observation and check shall be provided for the

foundation bolt before next grouting the concrete on the horizontal construction joint”.

Because the bolt and locating form panel may be displaced during concrete grouting, it is

required to check the bolt before next grouting on the construction joint to ensure the quality

of works.

7. Grouting

7.0.1 This is a supplemental clause.

The second grouting thickness for surface of equipment foundation is specified only in some

design drawings. In improving works, the original foundation may be used again and the

thickness of surface grouting usually depends on the actual conditions. So, it is necessary to

specify the grouting thickness. The margin of grouting at the top of foundation provided here

is specified based on the technical requirement of many construction drawings.

8. Acceptance of Works

8.0.1 The information for acceptance

of works is provided in reference with

the “specification for construction

and acceptance of concrete structure

works”(GB50204—92). Of which the

clause of providing the test report of

concrete mixture ratio is newly added.

Because the owner and supervisor

require the report of mixture ratio

with the exception of the report of

trial block of concrete and this

requirement is rational, so supplement

this clause here.